HD Construction Equipment 完成羣山新廠建設,廠房年產能包括 120 台坦克防務引擎、1,250 台 1–3 MWe 大型發電引擎,以及總容量 1,460 MWh 的電池組。

正文

HD Construction Equipment's new plant at its Gunsan campus. (Photo: HD Construction Equipment)

HD Construction Equipment's new plant at its Gunsan campus. (Photo: HD Construction Equipment)

HD Construction Equipment's new plant at its Gunsan campus. (Photo: HD Construction Equipment)
HD Construction Equipment's new plant at its Gunsan campus. (Photo: HD Construction Equipment)

HD Construction Equipment is responding to emerging energy demand with the completion of a new engine and battery pack manufacturing plant.

HD Construction Equipment said Oct. 28 that it held a completion ceremony for the new facility at its Gunsan campus in the Gunsan National Industrial Complex. The company invested 116.8 billion won over two years to develop the plant on a 62,700-square-meter site.

The new plant has annual production capacity for 120 defense engines for tanks, 1,250 large-scale power generation engines rated at 1–3 megawatts electric (MWe), and battery packs totaling 1,460 megawatt-hours (MWh). The battery pack capacity is sufficient to equip 9,400 electric buses.

HD Construction Equipment aims to meet rapidly growing demand for high-output generators used in AI data centers. It plans to begin mass production of a 1.3 MWe engine model in the first half of next year, followed by 3 MWe engines in 2028 and 2 MWe engines in 2029. One MWe is equivalent to the electricity consumed simultaneously by 1,000 households.

The company also plans to respond reliably to medium- and long-term growth in demand for defense engines used in tanks while expanding battery pack supplies. It aims to generate 2.5 trillion won in revenue from its engine business by 2030.