NERC 利益相關方通過涵蓋 AI 數據中心及加密貨幣挖礦設施的可靠性標準草案

Reliability Standards for AI Data Centers, Crypto Miners Move Closer to Adoption

AI 導讀

北美電力可靠性公司(NERC)的利益相關方已通過涵蓋 AI 數據中心、加密貨幣挖礦設施及其他計算負載的可靠性標準草案;草案下一步交由 NERC 董事會表決,若獲通過,再提交聯邦能源監管委員會(FERC)最終審批。

正文

Image 1: Informa LogoInforma TechTarget|

AI BusinessTechTarget InfrastructureInformationWeekLight Reading

Explore our brandsAn Informa TechTarget Publication

Data Center Knowledge Resource LibraryData Center WorldOnline EventsAdvertise

Image 2: Data Center Knowledge Logo

Newsletter Sign-Up

Newsletter Sign-Up

Infrastructure

Related Topics

Recent inInfrastructure

See All Infrastructure

Image 3: Nvidia company brand logoData Center Chips

Huang Resigns: Nvidia's AI Infrastructure Roadmap in QuestionHuang Resigns: Nvidia's AI Infrastructure Roadmap in Question

byBeth Pariseau

Nov 12, 2026

4 Min Read

Image 4: Hutto AI Data Center in Texas seen through the heat haze above crops in rural farmlandData Center Site Selection

The Rural Shift in Data Center DevelopmentThe Rural Shift in Data Center Development

byChristopher Tozzi

Nov 11, 2026

3 Min Read

Build & Design

Related Topics

Recent inBuild & Design

See All Build & Design

Image 5: Aerial View of Data Center Cooling Towers Under ConstructionData Center Construction

Labor Shortages Threaten Data Center SchedulesLabor Shortages Threaten Data Center Schedules

byNathan Eddy

Nov 13, 2026

3 Min Read

Image 6: General view of a power distribution power plant at sunsetEnergy & Power Supply

New Approaches to Data Center Power ProcurementNew Approaches to Data Center Power Procurement

byChristopher Tozzi

Nov 12, 2026

4 Min Read

Ops & Mgmt

Related Topics

Recent inOps & Mgmt

See All Ops & Mgmt

Image 7: Aerial View of Data Center Cooling Towers Under ConstructionData Center Construction

Labor Shortages Threaten Data Center SchedulesLabor Shortages Threaten Data Center Schedules

byNathan Eddy

Nov 13, 2026

3 Min Read

Image 8: General view of a power distribution power plant at sunsetEnergy & Power Supply

New Approaches to Data Center Power ProcurementNew Approaches to Data Center Power Procurement

byChristopher Tozzi

Nov 12, 2026

4 Min Read

Business

Related Topics

Recent inBusiness

See All Business

Image 9: Magnifying Glass Focused on Dart and BullseyesData Center Construction

Winning Data Center Bids Starts with the Investment Tax CreditWinning Data Center Bids Starts with the Investment Tax Credit

byMatthew Noll,Holly Pazand 1 more

Nov 10, 2026

3 Min Read

Image 10: Close-up of bright red emergency shutdown switch on control panelAI Data Centers

Building AI Kill Switches in Data CentersBuilding AI Kill Switches in Data Centers

byChristopher Tozzi

Nov 9, 2026

5 Min Read

Security

Related Topics

Recent inSecurity

See all Security & Risk Mgmt

Image 11: TPU 8tx + TPU 8i Max product art by Google CloudData Center Chips

Google Adds TPU 8tx, 8i Max for Enterprise AIGoogle Adds TPU 8tx, 8i Max for Enterprise AI

byWylie Wong

Nov 9, 2026

3 Min Read

Image 12: Nvidia Holds Berlin GTCData Center Chips

Nvidia Probes Huang Ties as AI Industry Weighs the FalloutNvidia Probes Huang Ties as AI Industry Weighs the Fallout

byShane Snider

Nov 9, 2026

8 Min Read

Next-Gen

Related Topics

Recent inNext-Gen

See All Next-Gen

Image 13: Aerial View of Data Center Cooling Towers Under ConstructionData Center Construction

Labor Shortages Threaten Data Center SchedulesLabor Shortages Threaten Data Center Schedules

byNathan Eddy

Nov 13, 2026

3 Min Read

Image 14: Nvidia company brand logoData Center Chips

Huang Resigns: Nvidia's AI Infrastructure Roadmap in QuestionHuang Resigns: Nvidia's AI Infrastructure Roadmap in Question

byBeth Pariseau

Nov 12, 2026

4 Min Read

Sustainability

Related Topics

Recent inSustainability

See All Sustainability

Image 15: Row of large industrial energy generators with exhaust pipes and cooling unitsRegulations

Trump Onsite Power Push Meets AI Data Center RealityTrump Onsite Power Push Meets AI Data Center Reality

byDrew Robb

Nov 3, 2026

5 Min Read

Image 16: Coolant hoses and infrastructure for data serversCooling

Liquid Cooling Retrofits: Hard, but Sometimes Worth ItLiquid Cooling Retrofits: Hard, but Sometimes Worth It

byChristopher Tozzi

Nov 2, 2026

5 Min Read

More

Related Topics

Resource Library

Reliability Standards for AI Data Centers, Crypto Miners Move Closer to Adoption

The proposed rules must still be approved by NERC’s board and federal regulators. As written, they would apply to computational loads of 50 MW or more connected at voltage levels of at least 100 kV.

Image 17: Picture of Utility Dive

Utility DiveInforma TechTarget October 15, 2026

2 Min Read

Image 18: Aerial view of a data center being constructed among existing centers

Getty Images

This article was originally published on Utility Dive.

North American Electric Reliability Corp. stakeholders approved new reliability standards for AI data centers, crypto mining facilities and other computational loads – an important step toward finalization, the grid watchdog said Thursday.

The standards now head to the NERC Board of Trustees for a vote, and, if adopted, will be filed with the Federal Energy Regulatory Commission for final approval.

The proposed standards build on insights and research related to a Level 3 alert NERC issued in May after several incidents where data centers unexpectedly dropped load or oscillated demand rapidly, threatening the stability of regional grids. The alert included seven actions grid entities “must implement to address immediate risks posed by computational loads” while permanent rules are created, NERC said.

The new standards aim to “establish requirements to support the reliable integration of large computational loads into the bulk power system,” the reliability organization said in a statement.

Related:Trump Onsite Power Push Meets AI Data Center Reality

Electricity demand is increasing after decades of stagnant growth, with data centers, in particular, driving load projections. Summer peak demand across the bulk power system is forecast to grow by 224 GW over the next 10 years, a 24% increase from 2025 peak demand, NERC said in January.

“These loads are reshaping the demand profile and exposing reliability gaps in both operational and planning time horizons,” NERC said on its standards development project site.

Multiple standards for computational loads were developed as part of NERC Project 2026-02, including requirements around interconnection studies and modeling; operational data and communications; and load protection coordination and disturbance monitoring.

Among other requirements, the standards establish modeling data, verification, and reporting procedures “for development of planning horizon cases necessary to support analysis of the reliability of the interconnected transmission system.”

They are designed to ensure transmission operators, balancing authorities and reliability coordinators have computational load site data needed “to plan, monitor, and assess the reliable operation” of the bulk power system, and to establish communication capabilities “with predefined communications protocols to ensure prompt action to prevent or mitigate occurrences that adversely impact the reliability of the Bulk Power System.”

The standards would apply to computational loads greater than or equal to 50 MW, connected at voltage levels greater than or equal to 100 kV.

Related:Could the Societal Value of Workloads Shape Data Center Policy?

NERC’s board is expected to consider the new standards in the fourth quarter, based on development timelines in the proposals.

About the Author

Image 19: Utility Dive

Utility Dive

Informa TechTarget

Utility Dive provides in-depth journalism and insight into the most impactful news and trends shaping the utility industry.

See more from Utility Dive

Image 20: Add as a preferred source on Google

Want more Data Center Knowledge stories in your Google search results?

Add Us Now

Subscribe to the Data Center Knowledge Newsletter

Get analysis and expert insight on the latest in data center business and technology delivered to your inbox daily.

Newsletter Sign-Up

Recommendations

SponsoredImage 21: ZTE Powers High Efficiency AIDC with Robust Energy Infrastructure

ZTE Powers High Efficiency AIDC with Robust Energy Infrastructure

AI Data CentersImage 22: Extreme Close-up of illuminated servers

Can Optical AI Cut Data Center Inference Power Use? by Sean Michael Kerner Nov 06, 2026

CoolingImage 23: Cooling tower for a data center

Can Evaporative Cooling in Data Centers Still Make Sense? by Andy Patrizio Oct 23, 2026

Data Center ChipsImage 24: IT Engineer Servicing Part of a Supercomputer

GPU Lifespan in Data Centers: Physical vs. Economic by Christopher Tozzi Sep 08, 2026

Editor's Choice

See all

Image 25

Energy & Power Supply

PJM Strategy Targets Data Center Growth, but Policy Gaps Remain

PJM Strategy Targets Data Center Growth, but Policy Gaps Remain

Aug 21, 2026

Image 26: Data center large-load flexibility illustration

Energy & Power Supply

Can Large-Load Flexibility Ease Data Center Energy Concerns?

Can Large-Load Flexibility Ease Data Center Energy Concerns?

Aug 19, 2026

Image 27: suburban homes connected to a cloud glyph via glowing dotted lines

Edge Data Centers

Home-Based GPU Networks: Viable Supplements to AI Data Centers?

Home-Based GPU Networks: Viable Supplements to AI Data Centers?

Aug 18, 2026

Image 28: Malaysia data center illustration

Data Center Construction

APAC Data Center Pipeline Surges as AI Pre-Leasing Tightens Supply

APAC Data Center Pipeline Surges as AI Pre-Leasing Tightens Supply

Aug 17, 2026

Image 29: Virginia data center groundwater illustration

Data Center Site Selection

Virginia Report Finds Groundwater Running Dry for New Data Centers

Virginia Report Finds Groundwater Running Dry for New Data Centers

Jul 30, 2026

Want more Data Center Knowledge stories in your Google search results?

Image 30: Add as a Preferred Source on Google

Subscribe to the Data Center Knowledge Newsletter

Get analysis and expert insight on the latest in data center business and technology delivered to your inbox daily.

Newsletter Sign-Up

Image 31: Data Center World 2027 | May 24 – 27, 2027 | Nashville, TN

Data Center World 2027

Digital infrastructure is being rebuilt faster than ever. AI-driven demand, power constraints, and today's decisions will define the next decade. Navigating this shift takes more than information — it takes a trusted guide. That's Data Center World 2027: Innovation at Scale.

Learn More

Industry Voices

Image 32: Aerial View of Data Center Cooling Towers Under Construction

Data Center Construction

Labor Shortages Threaten Data Center Schedules

Labor Shortages Threaten Data Center Schedules

Nov 13, 2026

Image 33: Nvidia company brand logo

Data Center Chips

Huang Resigns: Nvidia's AI Infrastructure Roadmap in Question

Huang Resigns: Nvidia's AI Infrastructure Roadmap in Question

Nov 12, 2026

Image 34: Data Center World Power | Sept 21 – 23, 2026 | Dallas, TX

Data Center World POWER

Join the entire data center ecosystem September 21 – 23, 2026, at the Gaylord Texan Resort & Convention Center in Dallas, TX.

Learn More

Image 35: Data Center Knowledge Logo

Discover More

InformationWeekData Center WorldAFCOM

Working With Us

About UsMeet Our WritersReprintsAdvertiseContact Us

Join Us

Newsletter Sign-Up

Follow Us

Image 36: Informa Tech

Copyright © 2026 TechTarget, Inc. d/b/a Informa TechTarget. This website is owned and operated by Informa TechTarget, part of a global network that informs, influences and connects the world’s technology buyers and sellers. All copyright resides with them. Informa PLC’s registered office is 5 Howick Place, London SW1P 1WG. Registered in England and Wales. TechTarget, Inc.’s registered office is 275 Grove St. Newton, MA 02466.

Home|CCPA: Do not sell my personal info|Cookies|Privacy|Terms

Your Privacy Choices

Image 38

來源:Data Center Knowledge · datacenterknowledge.com