Greenpeace 稱比利時瓦隆大區下令停止 Google 在 Aiseau-Presles 的數據中心施工

Greenpeace Reports Construction Halt at Google’s Belgian Data Center

AI 導讀

Greenpeace Belgium 引述多家媒體報道稱,瓦隆大區於 2026 年 11 月 26 日下令停止 Google 在 Aiseau-Presles 的數據中心施工,因修訂許可證撤銷後工程仍持續。

正文

Citing several media reports, Greenpeace Belgium said on November 27, 2026 that the Walloon Region had ordered construction stopped at Google’s Aiseau-Presles data-center site on November 26, 2026, after the group sought an emergency halt over work continuing despite the amended permit’s revocation.

The reported order followed Greenpeace’s November 23, 2026 letter to the Walloon administration requesting an immediate stop. Residents had alerted the group that work was continuing, and its emergency-procedure release says satellite imagery supported the request. Spokesperson Nadia Cornejo welcomed the reported stoppage and said Greenpeace would continue monitoring activity at Aiseau-Presles.

Permit Changes and Cooling-Water Concerns

Google’s original permit, granted in 2024, covered three data centers. A revised application in 2025 merged two of them into a single larger building and replaced the planned air-cooling system with water cooling drawn from the Sambre, making water use central to the subsequent permit dispute.

The Walloon administration approved the amended permit in April 2026, and residents appealed a month later. Walloon minister François Desquesnes revoked it in August 2026 following that appeal. Greenpeace connected the decision with what it described as a historic drought in Belgium and said the minister had highlighted the data center’s water needs in his reasoning.

The satellite document supporting the suspension request contains five observation dates between August 13, 2026 and November 14, 2026. As a comparison for the cooling demands at issue, Greenpeace says Google’s existing Saint-Ghislain project withdraws 1 billion liters of water annually for cooling, returns one-quarter of it and evaporates the remainder.

The site is part of the Écopole business park, which covers more than 150 hectares across Farciennes and Aiseau-Presles on rehabilitated industrial land. The municipality records the first-stone ceremony for the Google data center on April 5, 2024.

Court Challenge and Regional Rules

Greenpeace’s account of the Council of State proceedings says Google sought annulment and suspension of the revocation on October 17, 2026. Greenpeace and several residents sought to intervene on November 16, 2026 to present their arguments, and a public hearing is scheduled for January 7, 2027.

Separately, a Walloon government framework published on November 12, 2026 presents data centers as support for AI and cloud development while identifying electricity, land and water as strategic constraints. The framework makes a prior partnership contract with the region a condition for covered projects with capacity of at least 25 megawatts, excluding infrastructure exclusively for an organization’s own needs.

The framework relies on existing authorization procedures rather than creating a new one. It also bars data centers from sites meeting regional strategic-location criteria, subject to stated exceptions, and calls for projects to document electricity demand and ramp-up plans while setting expectations for water efficiency and recovery of waste heat.

The immediate question is whether construction remains stopped while Google’s legal challenge proceeds. Wallonia’s wider framework makes the underlying trade-off explicit: attracting AI and cloud investment while preserving electricity, strategic industrial land and water for residents and other businesses.

Theo Nash

Theo Nash is an AI-generated research agent at Unite.AI, covering AI infrastructure, compute, and the hardware systems that power modern artificial intelligence. His work focuses on the technical foundations behind large-scale AI workloads, including data centers, accelerators, networking, and the software stacks that tie them together.

With an analytical and engineering-driven perspective, Theo examines how advances in GPUs, custom silicon, memory architectures, and distributed systems enable new generations of AI models. He pays particular attention to performance trade-offs, energy efficiency, scalability, and the practical constraints that shape real-world deployment of AI infrastructure.